Definition

TThe objectives of the Design Review for Hardware held before the project PDR are as follows:

  1. Review and validate the detailed definition of the H/W (boards + mechanical) from technical standpoint
  2. Ensure that the detailed definition of H/W meets all project requirements (incl. Marketing, Service, Manufacturing and Material)
  3. Clearly identify the risks related to H/W and possible contingencies
  4. Review status of ASICs and S/W work to ensure good co-ordination with H/W
  5. Perform last sanity check on refined plans (schedule and resources) for H/W detailed design work to be conducted during Detailed Design Stage

Questions

Technical assessment

  • Does the detailed definition of H/W meet the product specifications?
  • Are the technical options/methods proposed for H/W appropriate for the project (architecture + implementation plans)?
  • Is the choice of components (technology, type, characteristics, cost, availability) appropriate?
  • Have the key risks related to H/W been correctly identified and evaluated?
  • Are there any risks for H/W due to the status of ASICs definition?
  • Are there any risks for H/W due to the status of S/W definition?
  • What contingencies can we propose against those risks (eg type of simulations, # of revisions, schedule)?
  • Are the R&D test programs for H/W (Unit, Integration) appropriate?
  • What are the open issues which need to be addressed regarding H/W?

Cross-functional check

  • Does the H/W definition support the Marketing requirements?
  • Does the H/W definition support the Serviceability requirements?
  • Does the H/W definition support the Manufacturing requirements?
  • Does the H/W definition support the Manufacturing Test requirements?
  • Are there any BOM issues from the commodity/components engineers standpoint?
  • Have the Quality Control issues been addressed?

H/W schedule and resources

  • Is the proposed schedule for H/W detailed design work appropriate?
  • Are the corresponding resources appropriate (# of people, type of skills)?
  • From a H/W standpoint, are we ready to proceed to the Detailed Design stage?

Input

Marketing

  • MRD

Service

  • Serviceability objectives

R&D

H/W design

  • High-level H/W design plans (including diagnostic concept)
  • Block diagrams
  • Preliminary BOM
  • Mechanical top level constraints
  • H/W requirements in terms of S/W support for H/W

R&D Test

  • Initial Unit / Integration Test programs (incl. # of cycles for H/W)
  • Initial Engineering Test programs
  • Unit/Integration Test tools and equipment list

Manufacturing

  • Flow chart of Manufacturing processes
  • New technologies & trade-offs
  • Complexity and volume analysis
  • Project basics (updated)

Manufacturing Test

  • Updated Test Development plan and resource allocation
  • DFT at Block Diagram level
  • Test equipment requirements

Materials

  • Final supply strategy plan
  • Revised analysis of risk / lead-time / cost
  • BOM coverage vs qualified suppliers

Finance

  • Estimates of product GM in production (on a per component basis)

Deliverables

Updated H/W detailed definition

List of open issues related to H/W detailed definition

Updated H/W schedule and resources for Detailed Design Stage

CAD plan (schematics, simulations, etc.)

Guidelines