Production Testing Development and Validation

Stage: Design and Verification, Development, Product Release

Definition

Design and verification stage activities include:

  • Implement test plan
  • Develop S/W testing (Version 0)
  • Prepare availability of test equipment
  • Complete and release test procedures
  • Validate test equipment and procedures with prototype production

Development stage activities include:

  • Send S/W version 0 to contract manufacturer
  • Validate test equipment H/W and S/W version 0 with Pilot Build
  • Develop manufacturing test documentation
  • Update S/W version of test equipment during Pilot Build

Product Release stage activities (before FCS) include:

  • Finalize implementation of test S/W

Dependencies

This step should start after the Manufacturing Strategy and Test step (after CDR)

This step overlaps with the Engineering Prototypes step

This step overlaps with the Pilot Build step

This step ends at FCS

Input

DFT

Test plan

Draft of S/W testing for JTAG, functional, burn-in

BOM

Deliverables

For the design and verification stage Review:

  • Initial implementation of test H/W and S/W for ICT, Functional, Burn-In and System tests at the CM site (during Engineering Prototypes)
  • Updated Test Coverage Plan for the different stations (Plan vs. Actual)

For the development stage Review:

  • Updated test S/W version (also made available to CM)
  • Production test equipment updated after modifications

For FCS:

  • Test equipment fully operational

Responsibility

Manufacturing Test Engineer at Atrica

Resources

Workload

Competencies

2 FTE

Lead-times

-

Metrics

Fault Coverage

Diagnostic Level Isolation

Evaluation of sub-contractor performance:

  • Time needed to perform test
  • Technician ability to repair board

Guidelines

Test Coverage Plan for all Stations

Process Readiness Matrix

DFT Guidelines

ICT & JTAG Test Development Procedure

Test guidelines

New Product Introduction Guidelines (NPI)