Manufacturing Process Validation

Stage: Development

Definition

Development stage activities include:

  • Manage Pilot build
  • Perform production training
  • Perform first article approvals (Documentation, Jigs, Set-ups and prototype quality)
  • Perform final drawing reviews
  • Complete and release draft manufacturing process instructions and test procedures

Dependencies

This step should start at the beginning of the development stage

This step should finish at the end of the development stage

Input

Engineering prototypes builds reports include: Quality figures, DFX, Material status

Test strategy document

Deliverables

Reports on the build results (quantities, turn-around times, quality levels by yields, main DFX issues)

MRR that formally releases the product for the FCS and first production build

Responsibility

Manufacturing representative in project team (MPE)

Resources

Workload

Competencies

MPE (100%)

Lead-times

2 weeks for PCB turnaround

Metrics

New Product Introduction Readiness Metrics (including risks)

Updated NRE forecast tableUpdated GM and Cost analysis model

Project basics

Updated Project objectives (one page summary)

Production Readiness Matrix

Test coverage and yield table (targets)

Guidelines

Process (Vendors) validation procedure

New Product Introduction Guide (NPI)