Stage: Specification, Design and Verification
Definition |
Activities taking place before HDR include:
Activities taking place before PDR include:
Activities taking place before CDR include:
Activities taking place before Alpha Readiness Review include:
|
---|---|
Dependencies |
This step starts during the specification stage
This step overlaps with ASIC, H/W and S/W design steps Unit/Integration Test step and Engineering Test step start before this step is completed (see details in Unit/Integration, Engineering/System test steps) This step ends before execution of System Test |
Input |
Before HDR: MRD, Technical requirements, System architecture (draft)
Before PDR: H/W, S/W and ASIC design documents (draft) Before CDR: H/W, S/W and ASIC design documents Before Alpha Readiness Review: H/W, S/W and ASIC development documents |
Deliverables |
For HDR:
For PDR:
For CDR:
For Alpha Readiness Review:
|
Responsibility |
R&D Project Manager |
ResourcesWorkloadCompetencies |
The resources for Test Design and Development mostly come from developers
from project team
Unit test: every developer Integration test: 1 S/W, 1 H/W (1) Engineering test: HALT(1/2 person), Env. (1/2), "box" test (2), system test (1/2), PHY (1/2), Agency (1/2) |
Lead-times |
- |
Metrics |
Test coverage for each type of test
Test coverage vs # of resources # of bugs found vs # of test cases # of people vs # of test cases for each type of test |
Guidelines |